⑴ 中国广东揭阳污水处理厂怎样翻译成英文
楼上翻译的不错,不过按照英语习惯,大地址放后,小地址放前,这个是常识
Sewage Treatment Plant Jieyang City,Guangdong Province,China
⑵ 请各位好心的哥哥姐姐们再帮我翻译一段英文,感激不尽
Along with the economical development, Taizhou Gao Gangqu the instryand agriculture and the inhabitant domestic water quantity demannceasingly increases, the dirty water volume massively increases,simultaneously goes into proction one after another along with BinJiang instry garden area many projects the operation, causes thesewage ingredient all the more to be also complex neighbor, themassive sewage directly disperse into the water body, causes the BinJiang instry garden and Gao Gangqu water quality worsens day by day.The Taizhou second sewage treatment factory owner if uses in toprocess the Bin Jiang instry garden area and the Gao Gangqucomprehensive sewage. A Taizhou second sewage treatment plant issue of project processingwater volume scale presses 20000, instrial waste accounts for theproportion according to 50¨G the design. The second phased projectsprocessing scale is 60,000 minute two stages implementations, an issueof processing water volume scale presses 30000, the instrial wasteaccounts for the proportion according to 70¨G the idea, the secondstage is the Bin Jiang instry garden area as well as Gao Gangquactual development situation expands to 60,000 overall scales, theinstrial waste accounts for the proportion according to 70¨G theidea, after the second phased projects, the entire sewage treatmentplant design scale achieves 80000. According to Jiangsu Taizhou Bin Jiang instry garden area andTaizhou Gao Gangqu sewage water quality material which provides, aswell as the processing water request achieved a level discharges therequest. This article has compared the oxidation ditch and thetraditional active sludge method has the good and bad points, thisdesign used chooses the Carrow 塞尔 oxidation ditch craft to takethe sewage treatment the core craft, in front of sewage processeddivides into two parts: The first part for the sanitary sewage arepartial for Gao Gangqu, uses the grill well and 曝气 沉砂池; Thesecond part for the Bin Jiang instry garden area sewage, uses thegrill well, the adjustment pond and the advection at the beginning oftype sinks the pond. The sewage treatment core construction for theCarew 塞尔 oxidation ditch, the spoke flows the type two to sink thepond, the gas floating type sludge thickening pond, two levels tiresof in the oxygen the warm digestion tank and so on. Moreover, but alsohas established the office building, the chemical examinationbuilding, the warehouse, the machine repair and so on the attachedfacility. And acts according to the sewage treatment plant thearrangement principle and the request, has carried on the dirt waterworks plane arrangement and the elevation arrangement. Finally, aseries of questions which appeared to the Carew 塞尔 oxidation ditchmovement process in has carried on the preliminary discussion andproposed the practical feasible means. Key word: Sewage treatment Carew 塞尔 oxidation ditch sludgehandling
我用工具翻译的。。
⑶ 我急需一篇关于污水处理的英文文章要带译文 希望大家帮帮忙
有关SBR污水处理法的英文文献
(中文):
SBR( Sequencing Batch Reactor Activated Sludge Process )是一种好氧微生物污水处理技术,是连续进水、间歇排水的周期循环间歇曝气系统。该工艺集调节、初沉、曝气、二沉、生物脱氮等过程于一池,按不同的时间顺序进行各种目的不同的操作,全部过程都在一个池体内周而复始地进行,工艺流程简洁,布局紧凑合理,是一种先进的污水处理系统。该技术适用于处理市政生活污水和中低浓度有机工业废水,能有效地去除废水中BOD5和悬浮固体(SS),将废水中的氮化合物转成硝酸盐,进而转成氨气,使出水的氨氮(NH3-N)含量大大降低。与之相比较,传统的连续流水处理系统CFS( Continuous Flow System )是在空间上设置不同的设施而在同一时间内进行各种操作。该工艺将调节、初沉、曝气、二沉、生物脱氮等过程设于多个池内进行,限制了反应器的功能,扩大了使用空间和占地面积,使运行速度迟缓,空间和地面的有效利用率降低,不适应于大中城市工业废水、生活污水和其它多种复杂环境中各种废水处理的需要。
(英文):
SBR (Sequencing Batch Reactor Activated Sludge Process) is one kind of good oxygen microorganism sewage treatment technology, is enters the water, the intermittent draining water cycle of motion intermittence aeration system continuously.This craft collection adjustment, initially sinks, the aeration, two sinks, processes and so on biological denitrogenation in one, carries on each kind of goal different operation according to the different time order, the complete process all again and again carries on in a cell body, the technical process is succinct, layout compact reasonable, is one kind of advanced sewage treatment system.This technology is suitable for the processing municipal administration sanitary sewage and the low concentration organic instrial waste, can remove in effectively the waste water BOD5 and suspended solid (SS), transfers the waste water in nitrogen compound the nitrate, then transfers the ammonia, causes the water leakage the ammonia nitrogen (NH3-N) content to rece greatly.Compares with it, traditional continuum water disposal system CFS (Continuous Flow System) is establishes the different facility in the space to carry on each kind of operation ring the same period of time.This craft will adjust, initially sinks, the aeration, two sinks, processes and so on biological denitrogenation supposes Yu Duoge in the pond to carry on, has limited the reactor function, expanded the use space and the area, caused the running rate to be slow, spatial and the ground effective use factor reced, did not adapt in the big or media-sized cities instrial waste, the sanitary sewage and other many kinds of complex environment each kind of waste water processing need.
⑷ 谁能给我找篇关于污水处理的中英文翻译
1.1.2 编制原则
依靠科技、加强管理、优化网络、均衡施工。
1.1.3 编制指导思想
严格按照IS09001标准要求,与国际惯例接轨,参照了菲迪克条款对承建商的有关要求,力争使该施工组织设计能全面、系统、科学、有效地指导该工程的安装及调试直至试运行符合施工验收规范和业主要求,从而实现设计意图。
1.1.4 编制目的
确保某污水处理厂安装工程的施工进度、施工质量、施工安全、确保文明施工、环境保护、员工健康、实现业主愿望,确保用户满意。
1.2 工程概况
重庆市某污水处理厂二期工程是重庆市利用日本政府贷款建设的主城排水工程之一。本工程的实施将为重庆主城区的可持续发展创造安全的环境。
二期工程是在原一期工程的基础上,完成一级处理、二级生物处理、消毒及污泥处理工程,使污水处理达到国家一级排放标准后,排入长江。
重庆市某污水处理厂用来处理雨污合流的城市污水,二期工程设计旱季处理污水量为60万m3/d,雨季处理污水量为135万m3/d,二级生物处理过程。远期污水厂规模为处理污水量80万m3/d,雨季处理污水量165万m3/d,二级生物处理过程。
重庆市某污水处理厂二期工程由上海某设计研究院设计。
工期要求:合同生效后360天内(包括安装和完成预调试)。
1.3 工程特点
1.3.1该工程采取设备供货、安装及调试总承包方式招商,对投标人要求严,承建商负责按设计要求提供设备及各个单项设备的性能保证的供货,安装及试运行。同时负责污水处理厂出水水质达到国家一级排放标准,如果达不到所保证的性能,无论是在测试期还是在20个月的运行监理期间,承建商应对设备作必要的改进或更换以达到所保证的性能。
1.3.2安装技术要求高
工艺设备安装技术要求高。该工程将大量采用国内外先进设备及仪器仪表,安装精度的控制对调试致关重要,整个污水处理厂安装调试合格后将实现计算机管理。
1.3.3自动化程度高
本工程采用PLC集中与分散相接合的控制方式。对液位/界面、温度、压力、溶解氧、污泥浓度、酸碱度、流量、调节阀开启度、有害气体浓度、电压、电流、功率等实施测量控制,工艺设置CRT投影仪银幕进行显示。
1.3.4交叉作业多
地下管网、阀井、工艺设备预留孔与土建必须配合进行,存在大量交叉作业。
1.3.5露天作业多
露天作业受气候影响大,在施工中条件成熟的要抓紧时间实施,雨天作业要有相应的技术措施。
1.4工艺简介
采用A/A/O处理工艺
重庆市某污水处理厂二期处理程度为一级处理、二级生物处理、消毒及污泥处理,执行中华人民共和国国家标准GB8978—1996《污水综合排放标准》中的一级标准,即:BOD5≤20mg/1,SS≤20mg/1,CODcr≤60mg/1,NH3-N≤15mg/1,TP≤0.5mg/1。
该污水处理厂采用A/A/O生化处理工艺。它是在A/O工艺基础上增加了一个缺氧区,具有同步脱氮除磷的功能。
A/A/O工艺处理污水首先进入厌氧区,兼性厌氧发酵细菌将污水中可生物降解的有机物转化为VFA(挥发性脂肪酸类)这类低分子发酵中间产物。而聚磷菌可将其体内存储的聚磷酸盐分解,所释放的能量可供好氧的聚磷菌在厌氧环境下维持生存,另一部分能量还可供聚磷菌主动吸收环境中的VFA类低分子有机物,并以PHB(聚羟β丁酸)的形式在其体内储存起来。随后污水进入缺氧区,反硝化菌就利用好氧区回流混合液带来的硝酸盐,以及污水中可生物降解有机物作碳源进行反硝化,达到同时降低BOD5与脱氮的目的。接着污水进入曝气的好氧区,聚磷菌在吸收、利用污水中残剩的可生物降解有机物的同时,主要是通过分解体内储存的PHB释放能量来维持其生长繁殖。同时过量的摄取周围环境中的溶解磷,并以聚磷的形式在体内储积起来,使出水中溶解磷浓度达到最低。而有机物经厌氧区、缺氧区分别被聚磷和反硝化细菌利用后,到达好氧区时浓度已相当低,这有利于自养型硝化菌的生长繁殖,并通过硝化作用将氨氮转化为硝酸盐。非除磷的好氧性异养菌虽然也能存在,但他在厌氧区中受到严重的压抑,在好氧区又得不到充足的营养,因此在与其他生理类群的微生物竞争中处于相对劣势。排放的剩余污泥中,由于含有大量能超量储积聚磷的聚磷菌,污泥含磷量可以达到6%(干重)以上。从以上分析可以看出A/A/O工艺具有同步脱氮除磷的功能。
A/A/O工艺的优点是厌氧、缺氧、好氧交替运行,可以达到同时去除有机物、脱氮、除磷的目的,而且这种运行状况丝状菌不宜生长繁殖,基本不存在污泥膨胀问题。A/A/O工艺流程简单,总水力停留时间少于其他同类工艺,并且不需外加碳源,缺氧、缺氧段只进行缓速搅拌,运行费用低。
雨、污水经过上述处理合格,符合国家排放标准的污水直接排入长江。
⑸ 如何定义一个污水处理厂
中文名称:污水处理厂 英文名称:wastewater treatment plant 定义:对污水用物理、化学、生物的方法进行净化处理的工厂。 应用学科:资源科技(一级学科);水资源学(二级学科)
⑹ 污水处理厂的英文翻译 急!!!!
sewage treatment works
⑺ 污水处理厂一般流程用英语表述
污水处理厂一抄般流程
The general proceres for the waste water treatments.
污水袭经过格栅进入初沉池,再进入生物反应池,在进入二沉池,
The waste water is allowed to go through the filtering grids to the preliminary sedimentation pool, and then to the biological reaction pool, and again into the secondary sedimentation pool.
⑻ 城市污水处理厂英文怎么写
城市污水处理厂
[词典] municipal sewage plant; urban sewage treatment plant;
[例句]介绍了新沂市城市污水处理厂的污泥膨胀情况。
Abs tract: This paper introces the problem of sludge bulking in Xinyi city wastewater treatment plant.
⑼ 求英文翻译高手 翻译两篇污水处理的英文文献
楼上的素质也太低了点吧,用在线翻译出来的也来这混积分,没意思,我是帮不了你了,不过千万别用在线翻译的,会闹很多笑话的。